Public Works Current Construction Projects

Print
Press Enter to show all options, press Tab go to next option

 

FOR THE LATEST ON LONG-TERM CLOSURES AND DETOURS RELATED TO THE I-5 HOV PROJECT, PLEASE VISIT http://i-5info.com/

PLANNED PUBLIC WORKS STREET PROJECTS

BRACE, VALLEY, AND VERDUGO PARK RESTROOMS PROJECT
In May 2017, Public Works began a project that will provide the community with clean, refurbished, and completely modernized restroom facilities at Brace Canyon Park, Valley Park, and Verdugo Park (Lower Assembly Building). Each restroom will be renovated to comply with current Americans with Disabilities Act (ADA) requirements and California Building Code (CBC) standards. The project scope for the restrooms includes the removal and replacement of amenities with low maintenance finishes, electrical upgrades, new LED fixtures, painting, and roof work. Portable restrooms and hand-washing stations will be provided during the construction phase that is estimated to be completed in December 2017. For more information regarding this project, please contact Nat Sotelo at (818) 238-3860.

JOSLYN RESTROOM RENOVATION
This project will renovate four restrooms at the Joslyn adult center, which provides programs and essential services for many seniors in Burbank.  This project includes renovation of two restrooms in the center of the building and two restrooms located on the Olive Avenue side of the building. The restrooms will be renovated to comply with current California Building Code (CBC) standards and American with Disabilities Act (ADA) requirements. All finishes in the restrooms will be updated and renovations will include lighting, plumbing fixtures, and plumbing valves. 

To help reduce disruption during construction, renovation will occur in two phases.  Each phase will include one women’s restroom and one men’s restroom.  Ingress and egress for each phase is planned to continue uninterrupted throughout each phase to protect staff and patrons, and to expedite work activities. Parking off of N. Griffith Park Drive on the east side of the street is designated "no parking" to accommodate construction.  This project is expected to be completed by November 2017. For more information, please contact the Public Works Project Manager, Nat Sotelo at (818) 238-3860.

COURTHOUSE PARKING STRUCTURE ELEVATOR MODERNIZATION PROJECT
In May 2017, Public Works began upgrading the most frequently used passenger elevator (closest to Third Street) in the Courthouse Parking Structure, also known as the Angeleno Parking Structure. This project will upgrade the passenger elevator to modern standards and codes. During construction, the second passenger elevator will be accessible for use. The project is expected to be complete by December 2017. For more information, please contact the Public Works Department at (818) 238-3860.

I-5 WIDENING CONSTRUCTION (CALTRANS)
In May 2014, Caltrans began the multi-year I-5 widening/carpool lane/new interchanges project on the northbound I-5 on-ramp at Empire Avenue, Buena Vista Street, and Burbank Boulevard.  The next phase of construction will be the Empire Avenue underpass and temporary railroad tracks at Buena Vista Street.  For more information about this project, including closure dates, please contact Caltrans - http://i-5info.com/ or toll-free at (855) 454-6335.

SAN FERNANDO BOULEVARD/BURBANK BOULEVARD INTERSECTION IMPROVEMENT
The design is currently underway to widen portions of the intersection to provide a second right turn lane from southbound San Fernando Boulevard to Burbank Boulevard.  The modification will improve the traffic capacity of the intersection.  Pedestrian and bus stop improvements are also included in the project which is being funded by Measure R. 

N. SAN FERNANDO BOULEVARD SAFETY IMPROVEMENT PROJECT
In October 2017, Public Works plans to start construction on N. San Fernando Boulevard to improve safety. The project will install sidewalk bulbouts at Amherst Drive, Andover Drive, East Avenue, and Scott Road, upgrade traffic signals at Scott/Amherst/San Fernando and Delaware/San Fernando, and install bicycle lanes between Grismer Avenue and Walnut Avenue. Various locations adjacent to these intersections will be temporarily closed for construction work.  The project is funded by a federal grant and is anticipated to be completed by May 2018.   For additional information, please contact Jonathan Yee at (818) 238-3915.

VERDUGO AVENUE SAFETY IMPROVEMENT PROJECT
In June 2017, Public Works began construction on Verdugo Avenue to improve safety. The project will install flashing yellow arrows at Buena Vista/Verdugo and Hollywood/Verdugo, upgrade traffic signals at California/Verdugo and Catalina/Verdugo, install a rapid flashing beacon at Virginia/Verdugo, and install bicycle lanes from Hollywood Way to Clybourn Avenue. Various locations adjacent to these intersections may be temporarily closed for construction work.  The project is funded by a federal grant and is anticipated to be completed by January 2018.   For additional information, please contact Jonathan Yee at (818) 238-3915.