The existing campus at Ranch Lot Studios will be redeveloped to consist of:
  • A new 5 story, approximately 326, 000 square feet, LEED certified office building
  • 16 new sound stages of approximately 320,000 square feet with associated production space of approximately 216,000 square feet.
  • A new mill building of approximately 64,000 square feet.
  • A new 5 level parking garage.
  • Site improvements including modernized infrastructure and new landscaping.

Address:
411 N. Hollywood Way
Burbank, CA 91505

Timeline:

  • Submitted Application – December 2022
  • Non-Structural Demolition Start – September 2023
  • Project Construction Start – October 2023
  • Anticipated Completion – Fall 2025

 

Contact Information

Greg Mirza-Avakyan
Senior Planner